- The hole where the chimney is placed is dug.
- The excavation base is compacted.
- The excavation base is leveled using fine sand
![menhol-kur-1 (1)](https://subterra.com.tr/wp-content/uploads/2024/02/menhol-kur-1-1.png)
- Floteks inspection manhole is placed on a smooth ground.
- Filling and compaction is done in layers up to the bottom level of the pipe connection.
- Pipe connection is made in a proper and leak-proof manner.
![menhol-kur-2 (1)](https://subterra.com.tr/wp-content/uploads/2024/02/menhol-kur-2-1.png)
- The compaction process continues layer by layer.
- Floteks inspection manhole is filled and compacted up to 5-8cm from the top
- The cover is placed and the last layer is applied and compression is done.
![menhol-kur-3 (1)](https://subterra.com.tr/wp-content/uploads/2024/02/menhol-kur-3-1.png)